Workers of DSU-7 are laying asphalt concrete pavement on Nikolai Chernyshevsky Street, from 1 May Street to Marat Street, over a section of about one kilometer.
Preparatory work was carried out here before. Literally this week, new asphalt will also be laid on Taras Shevchenko Street, with a length of 800 meters.
As the deputy director of the Orsha branch of the utility company "Vitebsk Housing and Communal Services" Vyacheslav Panasenko told the journalist of the "Arshanskaya Gazeta":
– Next, we will move to the area of the railway station, where a large-scale repair of the upper layer of asphalt concrete pavement is planned on Konstantin Zaslonov Street, Vasily Molokov Street, and Pakhaizhnaya Street. Almost 2.5 km of asphalt will be replaced on these streets. This season, work is also planned in the city of Barani on Nikolai Sorokin Street and in the agrotown of Zubovo.